A construction worker loads debris into one of several labeled dumpsters outside Gateway, with hand-painted signs reading Metal Only and Wood Only.
Construction

How We Built It

Gateway earned TRUE Platinum for Construction in August 2026, the highest level of TRUE certification. It's the first public project to earn TRUE Platinum for Construction.

About the certification

TRUE (Total Resource Use and Efficiency) certifies how well a project keeps materials out of landfill. Gateway's construction earned 63 points. The journey began with precertification in September 2023.

It was Turner Construction's first TRUE project. Turner led implementation and documentation, in partnership with UC Berkeley's Cal Zero Waste and project partners.

View Certificate (TRUE Platinum for Construction, PDF, opens in a new tab) TRUE Facility Case Study: UC Berkeley Gateway (PDF) (opens in a new tab)

Construction at a Glance

  • TRUE Platinum 63 points, awarded August 2026
  • 99.01% Construction waste diverted from landfill
  • 66,751 tons Kept out of landfill, including soil and earthwork
  • ~$1.8M Saved through source separation

Diversion, month by month

TRUE requires at least 90% of waste to be diverted from landfill, along with more than 80 other certification requirements. Every haul from the site was weighed and tracked.

Construction diversion rate

Share of each month's hauled material kept out of landfill

Monthly hauling data. Certified diversion rate: 99.01%.
Show the monthly numbers

Source separation

Instead of one mixed dumpster, crews sorted major materials into dedicated containers on site. GroundForce coordinated hauling so each stream reached the right recycler.

Major materials diverted

Tons by material, metal and larger (excludes soil and earthwork)

Show all 13 material streams
Show the hauling cost chart

Hauling cost comparison

Estimated cost for the project's documented materials

About $1.8M saved. Turner tracked monthly disposal costs and recycling rebates, and compared them with the cost of mixed bins across 1,207 documented hauls.
Show the numbers

Reusable shipping

Several trades swapped single-use wood crates and pallets for shipping systems that go back and get used again.

Workers in safety vests unload a glass curtainwall panel from a steel reusable bunk, with stacks of empty bunks behind them.

Curtainwall bunks

100+ tons of timber saved

Permasteelisa North America (PNA) shipped and installed Gateway's glass curtainwall on reusable steel bunks instead of disposable wooden crates and pallets.

Lengths of capped ductwork resting on a wheeled reusable rack inside the building under construction.

More reusable containers

  • ACCO: reusable transport bunkers that protected ductwork during handling.
  • Cupertino: reusable containers for electrical components.

Circular construction

Three photos: a large tree on the Gateway site before construction, a round wooden table top on a white base, and a long curved wooden bench.

From tree to table

Trees cut down for construction were given a second life. Nicholas Harvey at Bay Area Redwood crafted their wood into tables that are now used on campus. Thank you, Nicholas!

Vermicomposting

Food scraps from the construction site went to UC Berkeley's vermicomposting program, where worms turned them into nutrient-rich compost that supports campus research.

Cleaner equipment, smarter monitoring

A green Bobcat T7X all-electric compact track loader on the Gateway construction site.

All-electric loader

30% battery left after the longest recorded shift
  • The first U.S. construction-project pilot of the Bobcat T7X all-electric loader.
  • Ran about 6 hours straight.
  • Operator feedback went back to Bobcat and Sunbelt Rentals.
Water and energy on site

Water monitoring

Construction water sources were metered and reviewed regularly. Monitoring caught a restroom leak of about 30,000 gallons a month, and it was fixed within a week.

Renewable diesel

Used in jobsite equipment other than generators, in line with California off-road equipment rules.

Temporary power

Most welding ran on temporary grid power instead of diesel welding generators.

Live energy metering

About 15 systems were metered, including main gear, welding skids, restrooms, and site trailers. Trends were reviewed monthly.

Lower-carbon materials

Embodied-carbon modeling guided product choices for Gateway's biggest materials.

Show the embodied-carbon chart

Embodied-carbon reductions

Compared with conventional material baselines (hatched = reduction)

Show the numbers
About each material

Curtainwall: 15% lower

The first U.S. facility-specific curtainwall Environmental Product Declaration (EPD), produced by Permasteelisa North America.

EcoSmart drywall: about 20% lower

5/8-inch Firecode X, compared with standard Type X drywall.

Lower-carbon concrete: 38% lower

Level 3 and above, with 30% slag replacement.

Steel and whole-building carbon

Electric arc furnace steel

Most standard steel sections, including wide flange, hollow tube, and plate, came from North American electric arc furnace plants that use recycled steel as feedstock.

EC3 pilot As-built estimate in progress

The schematic design estimate was 52.31 kg CO2e per square foot.

Meet the team who completed the construction certification

This team led Gateway's construction phase to TRUE Platinum and submitted it for certification.

  • Audrey Pollack
  • Reeya Randhawa
  • Anya Brink
  • Andrea Forero
  • Sam Bunke
  • Brett Stuckey
  • Mike Teixeira
About a dozen people in hard hats and safety vests stand in a row in front of sorting bins labeled Wood Only and Dry Only, with Gateway's curved glass facade behind them.
The project team on site during construction.
Two team members in hard hats and safety vests stand on an upper level of Gateway, with the Campanile behind them.
On site at Gateway.